Catch late supplier orders before customers do: purchase order tracking

Paloma team · 19 November 2026

Purchase order tracking follows each PO line from sending through supplier confirmation, shipment and receipt to the invoice. Buyers get confirmed dates, chase each line before shipment, rank delays by customer orders at risk, and tell customers once the new date is known. Those checks continue while suppliers make and ship the goods.

Each stage of a purchase order has a warning sign you can check while the line is still open.

StageWhat should happenWarning signWhat to do
SentThe supplier acknowledges the PONo reply after the agreed number of daysAsk for written confirmation with a date per line
ConfirmedA date per line, on or before the requested dateA confirmed date later than requested, or only part of the quantity confirmedDecide now: accept, split, or find another source
In productionThe supplier stays on the confirmed dateSilence as the ship date nearsCheck readiness before the ship date
ShippedDispatch details and a tracking or booking referenceNo dispatch details on the ship dateAsk what shipped and when it arrives
ReceivedThe full quantity arrives on timeA short or late receiptRecord it on the line and chase the balance
InvoicedThe invoice matches the receiptAn invoice for more than arrivedHold it until the difference is explained

Late orders warn you before the due date

Most late supplier orders show a sign days or weeks before the due date, and tracking that stops once the PO is sent misses it.

  • Find lines without dates. A PO line without a written date from the supplier is already at risk.
  • Spot gaps in confirmations. A later date or a confirmation covering only part of the quantity leaves the requested delivery unresolved.
  • Notice lines going quiet. Silence near the ship date, followed by missing dispatch details on the day, signals a line to chase.

Customers find out first when nobody looks at the PO line between sending and receiving. Start with open lines whose status still says “sent” and check whether the supplier has replied.

Purchase order tracking starts with confirmed dates

A written date for each PO line, kept separate from the date you requested, gives buyers a date to compare against at every later check.

  • Get a date per line. Agree how many days the supplier has to confirm each line after you send the PO.
  • Keep both dates visible. Separate requested and confirmed dates so a gap appears as soon as the supplier replies.
  • Put replies on the line. Record email, phone and voice-note replies on the PO line the same day they arrive.

A supplier’s “boss confirmed, 400 tons, same price” voice note confirms quantity and price but still leaves the delivery date open. Ask which date applies to that quantity and get the answer in writing.

Chase each line before its ship date

Check each PO line before its ship date, while another source or a change to the job sequence can still keep production on schedule.

  • Check goods are ready. Ask before the ship date, or before the booking cut-off when the goods travel by ocean.
  • Get the dispatch reference. On the ship date, ask what shipped, how much, and for the tracking or booking reference.
  • Check exposed lines more often. Follow up more frequently on single-source parts and materials with little stock cover.

For an ocean shipment, put the readiness check ahead of the booking cut-off in the buyer’s calendar. A reply received after that cut-off may leave the goods waiting for another sailing.

Rank late lines by customer orders at risk

Rank a late PO line by the job and customer order it feeds, so buyers chase the supplier whose delay puts the next customer date at risk.

  • Check the stock cover. A slip within your stock cover can wait, while a slip beyond it stops a job.
  • Find the next job. Identify the production order that needs the material and the day it needs to start.
  • Find the customer date. Connect that job to its customer order and check when the finished goods are due.

When several late deliveries compete for the buyer’s attention, chase the line feeding the earliest customer order at risk. Supply chain visibility that warns you before the line runs short traces one late container through stock and jobs to the customer orders it affects.

Pick the cheapest fix that saves the date

When a supplier delay is confirmed, compare the options in order of cost and agree the new date in writing.

  • Bring the needed quantity forward. Ask about a partial shipment or faster freight, with who pays agreed before anything moves.
  • Find stock at another source. Check another supplier or a transfer from another plant for the quantity the job needs.
  • Move the job into reach. Resequence production so the late material arrives before the job that uses it.

Compare the cost and arrival date for the quantity that keeps the affected job on schedule. Once you choose the fix, put the agreed new date on the PO line in writing.

Tell customers once you know the new date

Tell the customer the new delivery date and what you’re doing as soon as you know their order will move, before they ask.

  • Send the revised date promptly. Contact the customer once their order is affected and you have a new date to give.
  • Explain what changes for the order. State the new date, the cause in one line, and the action underway.
  • Assign one person to the order. Name the customer service contact or account owner who will send the update.

The customer update should name the affected order and use its revised delivery date. If the supplier’s new date changes again, that same person sends the next update for the order.

Measure supplier on-time delivery against confirmed dates

Manufacturers improve supplier on-time delivery by measuring suppliers against confirmed and requested dates, reviewing misses with them, and first fixing their own lead times.

  • Check receipts against confirmed dates. Count lines received on or before the supplier’s date to see how reliably that supplier delivers.
  • Check confirmations against requested dates. Count lines confirmed for your requested date to see whether the supplier can meet your lead times.
  • Correct dates in the ERP. Update old lead times and address POs placed inside the supplier’s lead time before reviewing misses.

Bring the missed PO lines to the supplier review, with the dates that show where each miss began. For a line placed too late, agree how far ahead the next PO needs to reach the supplier.

Write follow-up rules so no line goes quiet

Written follow-up rules turn open PO lines into a daily list for each buyer, with a clear time to ask, chase or route a line to someone.

  • Set checks for each material. Write when to request confirmation, when to chase, and which slips make a line at risk.
  • Sort the buyer’s daily list. Include confirmations due, approaching ship dates and at-risk lines, ordered by the customer due dates they feed.
  • Move orders and update plans. Paloma, the operations management platform, moves orders between systems and updates plans using your written rules. The system then checks production, stock and deliveries against those plans and flags slips while there’s time to act.

As How it works describes, the system connects your ERP, spreadsheets and other records in one warehouse you own. It acts where you’ve approved it and asks a person where you haven’t, including when a rule can’t settle an exception.

FAQ

What is the best way to track purchase orders?

The best way of tracking purchase orders is per PO line, with confirmed and requested dates together where buyers update them daily. Use the ERP’s PO record if it holds confirmed dates, or a spreadsheet when one buyer maintains it. Purchase order tracking in Excel that flags every late line covers the sheet’s columns and formulas.

What should we do when a supplier fails to deliver at all?

Cancel the supplier’s open balance in writing and move the outstanding quantity to another source or plant. Record the failed delivery against that supplier, including the affected PO lines and quantities. Check what the contract says about failed deliveries as you close the unfulfilled balance.

How do we track a PO line that arrives in several deliveries?

Track each delivery on its own line or schedule line, with its own quantity and confirmed date. Match each receipt to the delivery it covers. The outstanding balance then keeps a date of its own, and the first receipt closes only the quantity that arrived.

Who should chase late purchase orders, the buyer or the planner?

The buyer who placed the PO chases the supplier, and the planner identifies which late lines affect the production schedule. Both work from the same PO line and its dates. The buyer handles the supplier conversation while the planner checks what the reply means for the affected jobs.